Project Updates

Court Street – Phase 1

Temporary paving from Keasor Court to Fair Street will start Monday, November 12.  The road will be milled and regraded to provide a consistent driving surface and will paved by the end of this week, weather depending. We will then pave the road from Durkee Street to Keasor Court, from Fair Street to just past Cumberland Farms and on Fair Street Ext..

Unfortunately, due to weather and underground utilities, we were not able to do our final road work this year. We will be back in the spring to do two final drain connections, complete the sidewalks and final grade and pave.

Union Avenue – Elm Street to Stark Street

Select water, sewer and drainage work began in November.  The intent is to complete utility work in the Union/Elm/Clinton intersection this year.  The work will extend into the 2019 construction season and will include sewer, drain, roadway and sidewalk improvements.

For more information call:

Project Manager: Krista Larsen  528-6379 ext. 306